Name the change type

Identify whether the request changes composition, construction, finish, colour, quantity, timing or documents. Describe the new requirement precisely. A vague request to improve the material can lead to an untracked substitution, so explain which attribute should change and which must remain fixed.

Identify the baseline

Reference the current brief, sample, quotation and order documents. State which version is being changed and whether it was only discussed or formally confirmed. Keep that original version accessible so every participant can understand the difference.

Ask about the impacts

Request the effect on sample work, price, minimums, evidence and schedule as relevant. Do not assume a small visual adjustment has no commercial consequence. A change of colour quantity can affect programme conditions even when material construction is unchanged.

Record roles and replies

Name requester, evaluator and approver, with dates. Keep proposed, awaiting reply and confirmed states distinct. A message asking for a change is not acceptance by the other party. Record partial answers only against the matters they actually resolve.

Review approvals again

Determine which sample or document decisions depended on the changed property. A new sample version starts not reviewed. If an item or blend changes, revisit making and claim-evidence review as applicable. Approval of unrelated attributes should be described with its actual limited scope.

Synchronise the package

Update brief, specification, sample reference, quotation and order attachments affected by the accepted change. Label old files superseded, preserving them as history. Do not silently overwrite a value in one worksheet while the supplier or maker works from another version.

Your change register

Illustration: a buyer changes the navy allocation after quotation. They ask whether price and timing still apply and retain the earlier allocation until a revised agreement exists. Use the register below to show the request, its implications and the actual confirmation source.

Change ID/date/requester: [entry]
Baseline brief/sample/quote/order: [references]
Requested change: [old → proposed]
Fixed attributes to retain: [list]
Impact question | Evaluator | Reply | State
[sample / price / quantity / timing / evidence rows]
Approver and confirmation source/date: [record]
New revision and superseded files: [list]
Outstanding tasks and owner: [entries]
Track the Sample and Specification Version Together →Build a Clear Fabric Order Handover →Know Which Fabric Quote Is Still Applicable →